Within the framework of the project, we installed and commissioned 5 battery energy storage systems (BESS) with a capacity of 50kW/160kWh at 3 different locations.
Challenge: We had to overcome significant challenges during the project, as all three locations had different terrain and environmental conditions. Integrating the energy storage systems into the existing energy management IT system was an important part of the task.
Solution: Our expert team carefully selected the most suitable BESS that could meet the various environmental and technical requirements. Before the installation, we thoroughly assessed the site conditions and developed a detailed schedule for the professional installation of the systems. After commissioning, we handed over the finished systems to the customer, ensuring that all components were working smoothly. In addition, we provided full support for the IT system integration and were constantly available for post-installation fine-tuning.